Just to make it very clear, what follows is NOT WRITTEN BY ME. I am NOT the project manager of the Miramar Town Centre Upgrade, that role is taken up by Kevin Murphy ( kevin.murphy@wcc.govt.nz ). If you want to get the email yourself, and I heartily recommend it, then 'subscribe' by sending an email to miramar@wcc.govt.nz Project home: http://wellington.govt.nz/your-council/projects/miramar What’s happened this week Installation of drainage in the new car park has been completed, kerb and channel has been poured and work has started on laying the basecourse ready to receive the new surface. The entrance to the new car park from Miramar Avenue has been prepared as part of this work. Work has also commenced on stabilizing the footings for the tram shelter in preparation for a new concrete floor slab to be poured. What’s happening next week “Boxing” and reinforcing steel will be installed at the car park entrance and, weather permitting, concrete will be poured to f